Delight Technology Center Data Center Annexation & Development

Joliet

Summary

PowerHouse and Hillwood are seeking annexation, rezoning, and preliminary PUD approval for an 800-acre data center campus featuring 24 buildings. While union trade workers and economists praise the thousands of construction jobs and millions in tax revenue, local residents and environmental advocates strongly oppose the project over fears of soaring electric bills, water depletion, and severe noise and air pollution.

At a glance

Total mentions
12
Last 30 days
0

Last discussed Jun 3, 2026.

Impact analysis

💰Financial impact

Project expected to generate approximately $310 million in property taxes over 30 years and $40 million in utility taxes without municipal tax abatements.

✅Who benefits

Local union construction workers, school districts receiving property tax revenue, and the city's commercial tax base.

⚠️Who could be affected

Nearby residents facing potential noise pollution, property value concerns, and increased utility demand risks.

Mentions & discussions (26)

MeetingJun 3, 2026

Comprehensive Plan Advisory Committee - Jun 3, 2026

Committee members raised concerns about ensuring new housing developments have adequate utilities, cell service, and broadband internet access to support families and educational needs.

MeetingApr 7, 2026

City Council Meeting - Apr 7, 2026

Residents voiced frustration during public comment regarding previous city council votes to approve large data center projects, stating that community opposition was ignored and demanding better dialogue between residents and elected officials.

Chicago Construction NewsMar 24, 2026

Data center approval a ‘win-win’ for Joliet and skilled tradespeople

Data center approval a ‘win-win’ for Joliet and skilled tradespeople Chicago Construction News

MeetingMar 23, 2026approved

2026-03-19 Council - Mar 23, 2026

Hillwood's 795-acre data center project near South Rowell Road and Bernhardt Road was hotly debated by residents and ultimately approved by the city council. Supporters highlighted millions in tax revenues for local schools and community benefits, while opponents raised concerns about water use, electricity demand, noise, and environmental impacts.

Shaw LocalMar 20, 2026

Joliet OKs controversial 795-acre data center

Joliet OKs controversial 795-acre data center Shaw Local

MeetingMar 19, 2026

City Council Meeting - Continuation of the City Council Meeting – Reconvened - Mar 19, 2026

Hillwood's massive 795-acre data center project was approved by the city council despite intense community pushback. Supporters highlight union jobs and millions in tax revenue for schools, while opponents raised serious concerns about water usage, lack of public notice, and rising utility bills.

ABC7 ChicagoMar 19, 2026

Data centers in Illinois: City council approves plans for Joliet data center near Bernhard and Rowell, east of Speedway

Data centers in Illinois: City council approves plans for Joliet data center near Bernhard and Rowell, east of Speedway ABC7 Chicago

PatchMar 19, 2026

Joliet Technology Center Vote By City Council Goes 8 To 1, Audience Claps With Approval

Joliet Technology Center Vote By City Council Goes 8 To 1, Audience Claps With Approval Patch

PatchMar 17, 2026

'How Much Money Is Joliet City Planner Going To Get From This Project?' Data Center Foe Asks Council

'How Much Money Is Joliet City Planner Going To Get From This Project?' Data Center Foe Asks Council Patch

CBS NewsMar 17, 2026

Joliet data center decision delayed until Thursday

Joliet data center decision delayed until Thursday CBS News

Shaw LocalMar 17, 2026

More than 6 hours of public hearing forces Joliet City Council vote on data center to Thursday

More than 6 hours of public hearing forces Joliet City Council vote on data center to Thursday Shaw Local

NBC 5 ChicagoMar 17, 2026

Vote on Joliet data center proposal postponed after marathon public meeting

Vote on Joliet data center proposal postponed after marathon public meeting NBC 5 Chicago

MeetingMar 16, 2026approved

City Council Meeting - Mar 16, 2026

Hillwood and Powerhouse Data Centers are proposing a massive 800-acre data center campus featuring 24 buildings on the southeast side of Joliet. While proponents highlight billions in private investment, union jobs, and tax revenue, residents and community groups have raised intense concerns regarding water consumption from a strained aquifer, noise pollution, and rising electricity costs.

PatchMar 16, 2026

Joliet Data Center Doesn't Get Yes Or No, City Council Meeting Passes Midnight, Vote Moved To Thursday

Joliet Data Center Doesn't Get Yes Or No, City Council Meeting Passes Midnight, Vote Moved To Thursday Patch

ABC7 ChicagoMar 16, 2026

Data centers in Illinois: City council considers plans for Joliet data center near Bernhard and Rowell, east of Speedway

Data centers in Illinois: City council considers plans for Joliet data center near Bernhard and Rowell, east of Speedway ABC7 Chicago

WGN-TVMar 16, 2026

795-acre proposed data center to take center stage at Joliet City Council meeting

795-acre proposed data center to take center stage at Joliet City Council meeting WGN-TV

The Times WeeklyMar 10, 2026

Joliet residents express opposition to proposed data center

Joliet residents express opposition to proposed data center The Times Weekly

MeetingMar 5, 2026

Plan Commission - Mar 5, 2026

PowerHouse and Hillwood are seeking annexation, rezoning, and preliminary PUD approval for an 800-acre data center campus featuring 24 buildings. While union trade workers and economists praise the thousands of construction jobs and millions in tax revenue, local residents and environmental advocates strongly oppose the project over fears of soaring electric bills, water depletion, and severe noise and air pollution.

MeetingMar 3, 2026

City Council Meeting - Mar 3, 2026

Multiple residents spoke out against a proposed data center, raising concerns about air quality, diesel generator emissions, water usage, and lack of transparency.

MeetingFeb 20, 2026

Council - Feb 20, 2026

Multiple residents spoke out against the proposed Joliet Technology Center data center, citing concerns about skyrocketing electricity costs, massive water and energy consumption, and inflated job creation claims.

MeetingFeb 17, 2026

City Council Meeting - Feb 17, 2026

Multiple residents spoke out during public comment against the proposed Joliet Technology Center data center, citing concerns over high electricity prices, water usage, and inflated job creation claims.

MeetingFeb 17, 2026

Public Service Committee - Feb 17, 2026

Committee members questioned staff about water consumption for the Hillwood development. Staff explained that the developer shifted to a closed-loop cooling system, capping daily water use at 300,000 gallons mostly dedicated to landscaping irrigation rather than millions of gallons for industrial cooling.

MeetingFeb 6, 2026

2026-01-20 Council - Feb 6, 2026

Numerous residents spoke during public comment to voice strong opposition to a proposed massive data center development in the area, citing severe concerns over surging electricity rates, strain on local power grids, water consumption, and environmental degradation.

MeetingJan 20, 2026

City Council Meeting - Jan 20, 2026

Numerous residents spoke out against a proposed large-scale AI data center in Joliet, expressing deep concerns over massive power grid strain, skyrocketing electric utility bills, water aquifer depletion, chemical pollution, and lack of transparency from city officials.

Shaw LocalDec 20, 2025

Joliet residents rise up again against proposed data center

Joliet residents rise up again against proposed data center Shaw Local

PatchOct 13, 2025

Joliet's 795-Acre Data Center Should Be Pulled Off Meeting Agenda: City Planner

Joliet's 795-Acre Data Center Should Be Pulled Off Meeting Agenda: City Planner Patch

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Joliet

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.